Gravel Connect

Ridgeline Grading & Excavation · Colorado Springs, CO

Demo run saves in this browser only. Not shared accounts, not secure storage.

TR-1042 · 5× Side Dump

Ridgeline Grading & Excavation → Stone Hollow Trucking · Structural base — Class 2

Job details

Project

P-2411 · Highway 24 Widening — Phase 2

Work order

WO-101 · Roadway subgrade & aggregate base course

Cost code

02-230 · Import — Structural Base Trucking

Start

Oct 26, 2026 at 06:30

Pickup

Valley Pit & Aggregate — Scale House 1

Delivery

US-24 STA 141+00 subgrade

Estimated quantity

9 hours/truck

Commitment

4 of 5 trucks

Notes

One truck short — Stone Hollow has SH-11 in the shop.

Terms lockedBoth parties accepted

Rate type

Hourly

Rate

$118.00/hr

Minimum hours (optional)

None

Standby

$85.00/hr

Overtime

$145.00/hr

Fuel surcharge

None

Mobilization

None

Custom terms

Overtime after 10 hours on site.

Accepted by Ridgeline Grading & Excavation

Dana Whitfield · Oct 24, 2026 · 11:05 AM

Accepted by Stone Hollow Trucking

Alicia Stone · Oct 24, 2026 · 1:47 PM

Locked terms cannot be edited in place. Any change must be raised as a change request so both sides review it.

Change request

Accepted terms are never edited in place. Propose a change and the other side decides.

Rate, minimums, standby, surcharges and custom terms all stay locked until a change request is accepted by the other party.

Audit trail

Append-only record of commitments, terms and changes.

  • Committed 4 of 5 trucks (SH-11 down for repair) and accepted terms.

    Alicia Stone · Stone Hollow Trucking · Oct 24, 2026 · 1:47 PM

  • Request sent to Stone Hollow Trucking — 5 side dumps, hourly.

    Dana Whitfield · Ridgeline Grading & Excavation · Oct 23, 2026 · 4:00 PM