TR-1041 · 5× End Dump

Ridgeline Grading & Excavation → Canyon Haul LLC · Road mix — CDOT Class 6

Job details

Project

P-2411 · Highway 24 Widening — Phase 2

Work order

WO-101 · Roadway subgrade & aggregate base course

Cost code

02-220 · Haul — Road Mix (CDOT Class 6)

Start

Oct 26, 2026 at 06:00

Pickup

Valley Pit & Aggregate — Scale House 2, Widefield

Delivery

US-24 STA 128+00 stockpile

Estimated quantity

1,250 tons/day

Commitment

5 of 5 trucks

Notes

Check in at scale house, ask for road mix ticketing under Ridgeline account.

Terms lockedBoth parties accepted

Rate type

Per ton

Rate

$8.75/ton

Minimum hours (optional)

4 hrs

Standby

$85.00/hr

Overtime

Not included

Fuel surcharge

4.5%

Mobilization

$350.00

Custom terms

Tarped loads required. 30-minute paid standby cap per trip.

Accepted by Ridgeline Grading & Excavation

Dana Whitfield · Oct 23, 2026 · 3:42 PM

Accepted by Canyon Haul LLC

Ray Ellison · Oct 23, 2026 · 5:08 PM

Locked terms cannot be edited in place. Any change must be raised as a change request so both sides review it.

Change request

Accepted terms are never edited in place. Propose a change and the other side decides.

Rate, minimums, standby, surcharges and custom terms all stay locked until a change request is accepted by the other party.

Change requests

Old vs proposed, side by side.

  • Ray Ellison · Canyon Haul LLC

    Oct 26, 2026 · 8:15 AM

    CDOT closed the Fountain Blvd crossing — haul route is 3.4 miles longer each way starting tomorrow.

    Pending

    Current accepted

    $8.75/ton

    Fuel 4.5% · Mobilization $350.00

    Proposed

    $9.10/ton

    Fuel 4.5% · Mobilization $350.00

Audit trail

Append-only record of commitments, terms and changes.

  • Change request opened: rate 8.75 -> 9.10 per ton (route detour).

    Ray Ellison · Canyon Haul LLC · Oct 26, 2026 · 8:15 AM

  • Committed 5 of 5 trucks and accepted terms.

    Ray Ellison · Canyon Haul LLC · Oct 23, 2026 · 5:08 PM

  • Request sent to Canyon Haul LLC — 5 end dumps.

    Dana Whitfield · Ridgeline Grading & Excavation · Oct 22, 2026 · 9:12 AM