TR-1041 · 5× End Dump
Ridgeline Grading & Excavation → Canyon Haul LLC · Road mix — CDOT Class 6
Job details
Project
P-2411 · Highway 24 Widening — Phase 2
Work order
WO-101 · Roadway subgrade & aggregate base course
Cost code
02-220 · Haul — Road Mix (CDOT Class 6)
Start
Oct 26, 2026 at 06:00
Pickup
Valley Pit & Aggregate — Scale House 2, Widefield
Delivery
US-24 STA 128+00 stockpile
Estimated quantity
1,250 tons/day
Commitment
5 of 5 trucks
Notes
Check in at scale house, ask for road mix ticketing under Ridgeline account.
Rate type
Per ton
Rate
$8.75/ton
Minimum hours (optional)
4 hrs
Standby
$85.00/hr
Overtime
Not included
Fuel surcharge
4.5%
Mobilization
$350.00
Custom terms
Tarped loads required. 30-minute paid standby cap per trip.
Accepted by Ridgeline Grading & Excavation
Dana Whitfield · Oct 23, 2026 · 3:42 PM
Accepted by Canyon Haul LLC
Ray Ellison · Oct 23, 2026 · 5:08 PM
Locked terms cannot be edited in place. Any change must be raised as a change request so both sides review it.
Change request
Accepted terms are never edited in place. Propose a change and the other side decides.
Rate, minimums, standby, surcharges and custom terms all stay locked until a change request is accepted by the other party.
Change requests
Old vs proposed, side by side.
- Pending
Ray Ellison · Canyon Haul LLC
Oct 26, 2026 · 8:15 AM
CDOT closed the Fountain Blvd crossing — haul route is 3.4 miles longer each way starting tomorrow.
Current accepted
$8.75/ton
Fuel 4.5% · Mobilization $350.00
Proposed
$9.10/ton
Fuel 4.5% · Mobilization $350.00
Audit trail
Append-only record of commitments, terms and changes.
Change request opened: rate 8.75 -> 9.10 per ton (route detour).
Ray Ellison · Canyon Haul LLC · Oct 26, 2026 · 8:15 AM
Committed 5 of 5 trucks and accepted terms.
Ray Ellison · Canyon Haul LLC · Oct 23, 2026 · 5:08 PM
Request sent to Canyon Haul LLC — 5 end dumps.
Dana Whitfield · Ridgeline Grading & Excavation · Oct 22, 2026 · 9:12 AM